9th December, 2021

On Monday, the deck for level one was poured at Wishlist Centre and by Friday, the blockwork and columns will be finished for level two.  

The level two slab pour is scheduled for the second week of 2022, pending sunshine and then the installation of the windows will commence.

Origin Cranes will be working their hydraulic crane on-site until early March as the structure is constructed, and to ensure the emergency helicopter airspace is not impacted, the jib can be sucked down in as little as 1.5 minutes.

Currently, there are between 25-35 construction workers onsite daily, and this number will double in January 2022, with a peak of 200 workers expected on-site in early March.

See the birds-eye view of the project in the video below.

The site will shut down on December 17 with trades returning on January 5, 2022.